| Assessment Year | 2012 |
|---|---|
| Principal Product | Offshore service vessels |
| NAICS | 336612: Boat Building |
| SIC | 3732: Boat Building and Repairing |
| Sales Range | $100 M to 500M |
| # of Employees | 500 |
| Plant Area |
256,625
ft2
|
| Annual Production | 4
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Mississippi |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $404,625 | 5,083,200 |
kWh
|
$0.080 |
| Electricity Fees | $20,568 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $54,656 | $11,200 |
$52,012
653,421
kWh
|
$2,644 | - | |
| 02 | 2.7134: Use photocell controls | $3,740 | $120 |
$3,559
44,713
kWh
|
$181 | - | |
| 03 | 4.611: Begin a practice of predictive / preventative maintenance | $2,943 | $630 |
$1,373
17,254
kWh
|
$70 | $1,500 | |
| 04 | 2.7224: Reduce space conditioning during non-working hours | $1,500 | $660 |
$1,427
17,922
kWh
|
$73 | - | |
| 05 | 2.6211: Conserve energy by efficient use of vending machines | $584 | $735 |
$556
6,989
kWh
|
$28 | - | |
| 06 | 2.7135: Install occupancy sensors | $419 | $735 |
$399
5,007
kWh
|
$20 | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $200 | $155 |
$190
2,391
kWh
|
$10 | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $188 | $213 |
$179
2,245
kWh
|
$9 | - | |
| 09 | 4.611: Begin a practice of predictive / preventative maintenance | $10,920 | $2,084 | - | - | $10,920 | |
| TOTAL RECOMMENDED | $75,150 | $16,532 |
$59,695
749,942
kWh
|
$3,035 | $12,420 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs