ITAC Assessment: AM0797
ITAC logo
ITAC Assessment: AM0797
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Water, juice, and carbonated beverages
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 310,000
ft2
Annual Production 35,600,000
pieces
Production Hrs. Annual 8,592
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $734,923 16,303,382
kWh
Electricity Demand $324,982 37,111
kW-mo/yr
Electricity Fees $23,532 -
Natural Gas $256,640 62,285
MMBtu
Waste Disposal Costs
Water Usage $35 5
Tgal
TOTAL YEARLY COSTS $1,340,112
RECOMMENDED SAVINGS* $66,199 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $66,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $17,410 $34,210 - $17,410
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,400 $2,000 $13,500
299,000
kWh
$3,900
-
kW-mo/yr
- -
03 2.2441: Preheat boiler makeup water with waste process heat $9,500 $20,000 - - $9,500
-
MMBtu
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,799 $400 $4,129
91,500
kWh
$1,670
-
kW-mo/yr
- -
05 2.2511: Insulate bare equipment $5,725 $420 $4,455
99,000
kWh
$1,270
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,280 $22,200 $2,250
50,000
kWh
$670
-
kW-mo/yr
- $360
07 2.4314: Use synthetic lubricant $5,500 $200 $3,900
87,600
kWh
$1,600
-
kW-mo/yr
- -
08 2.7111: Reduce illumination to minimum necessary levels $860 $60 $550
12,400
kWh
$310
-
kW-mo/yr
- -
09 2.6218: Turn off equipment when not in use $725 $730 $725
16,100
kWh
- - -
TOTAL RECOMMENDED $66,199 $80,220 $29,509
655,600
kWh
$26,830
-
kW-mo/yr
$9,500
-
MMBtu
$360
TOTAL IMPLEMENTED $66,199 $80,220 $29,509
655,600
kWh
$26,830
-
kW-mo/yr
$9,500
-
MMBtu
$360
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs