Assessment Year | 2011 |
---|---|
Principal Product | oil field tools |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 84 |
Plant Area |
65,000
ft2
|
Annual Production | 325,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,882 | 1,141,700 |
kWh
|
$0.069 |
Electricity Demand | $48,400 | 4,652 |
kW-mo/yr
|
$10.40 |
LPG | $51,407 | 2,084 |
MMBtu
|
$24.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,948 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,435 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,312 | $6,320 |
$15,596
225,738
kWh
|
$1,716
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2511: Insulate bare equipment | $15,407 | $440 | - | - |
$15,407
-
MMBtu
|
- | - | - | |
03 | 4.611: Begin a practice of predictive / preventative maintenance | $8,131 | $900 |
$6,631
95,981
kWh
|
- | - | - | - | $1,500 | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,716 | $45 |
$3,716
53,785
kWh
|
- | - | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $2,857 | $3,750 |
$2,857
41,356
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,159 | $700 |
$459
6,639
kWh
|
$95
-
kW-mo/yr
|
- | $362 | $243 | - | |
07 | 2.6211: Conserve energy by efficient use of vending machines | $729 | $919 |
$604
8,736
kWh
|
$125
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $333 | $160 |
$219
3,163
kWh
|
$114
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7135: Install occupancy sensors | $304 | $700 |
$304
4,399
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $49,948 | $13,934 |
$30,386
439,797
kWh
|
$2,050
-
kW-mo/yr
|
$15,407
-
MMBtu
|
$362 | $243 | $1,500 | ||
TOTAL IMPLEMENTED | $36,435 | $6,805 |
$19,312
279,523
kWh
|
$1,716
-
kW-mo/yr
|
$15,407
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs