ITAC Assessment: LL0347
ITAC logo
ITAC Assessment: LL0347
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Sand and Gravel
NAICS 212322: Industrial Sand Mining
SIC 1446: Industrial Sand
Sales Range $5
M
to 10
M
# of Employees 17
Plant Area 4,800,000
ft2
Annual Production 1,100,000
ton
Production Hrs. Annual 8,112
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $434,510 8,899,800
kWh
Electricity Demand $170,089 24,298
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,825 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $53,145 $166,176 $53,145
1,088,593
kWh
- - -
02 4.611: Begin a practice of predictive / preventative maintenance $3,308 $330 $1,808
37,033
kWh
- - $1,500
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,835 $30 $1,835
37,580
kWh
- - -
04 2.7224: Reduce space conditioning during non-working hours $1,754 $180 $1,754
35,942
kWh
- - -
05 2.7134: Use photocell controls $352 $30 $352
7,212
kWh
- - -
06 2.7135: Install occupancy sensors $223 $525 $223
4,570
kWh
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $99 $70 $32
664
kWh
$6
-
kW-mo/yr
$61 -
08 2.6211: Conserve energy by efficient use of vending machines $85 $184 $85
1,747
kWh
- - -
09 2.7224: Reduce space conditioning during non-working hours $24 $66 $24
487
kWh
- - -
TOTAL RECOMMENDED $60,825 $167,591 $59,258
1,213,828
kWh
$6
-
kW-mo/yr
$61 $1,500
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs