| Assessment Year | 2009 |
|---|---|
| Principal Product | Used furniture and clothing |
| NAICS | 453310: Used Merchandise Stores |
| SIC | 5932: Used Merchandise Stores |
| Sales Range | less than $500 k |
| # of Employees | 15 |
| Plant Area |
30,000
ft2
|
| Annual Production | 25,000
pieces
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $15,847 | 154,380 |
kWh
|
$0.10 |
| Electricity Fees | $379 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,124 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,807 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.611: Begin a practice of predictive / preventative maintenance | $9,807 | $630 |
$9,577
93,300
kWh
|
$230 | - | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $2,839 | $150 |
$2,772
27,000
kWh
|
$67 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,307 | $700 |
$684
6,658
kWh
|
$16 | $607 | |
| 04 | 2.6211: Conserve energy by efficient use of vending machines | $735 | $623 |
$718
6,989
kWh
|
$17 | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $203 | $90 |
$198
1,929
kWh
|
$5 | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $170 | $66 |
$166
1,613
kWh
|
$4 | - | |
| 07 | 2.7135: Install occupancy sensors | $63 | $90 |
$62
599
kWh
|
$1 | - | |
| TOTAL RECOMMENDED | $15,124 | $2,349 |
$14,177
138,088
kWh
|
$340 | $607 | ||
| TOTAL IMPLEMENTED | $9,807 | $630 |
$9,577
93,300
kWh
|
$230 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs