Assessment Year | 2008 |
---|---|
Principal Product | Paper mill rollers |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 37 |
Plant Area |
43,000
ft2
|
Annual Production | 520
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,188 | 2,330,720 |
kWh
|
$0.077 |
Electricity Fees | $6,847 | - |
|
- |
Natural Gas | $80,459 | 8,626 |
MMBtu
|
$9.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,528 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,861 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,295 | $660 |
$8,955
115,836
kWh
|
$340 | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $9,039 | $4,182 |
$8,708
112,637
kWh
|
$331 | - | |
03 | 2.2135: Repair and eliminate steam leaks | $4,566 | $730 | - | - |
$4,566
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,640 | $7,300 |
$1,580
20,442
kWh
|
$60 | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $986 | $264 |
$950
12,289
kWh
|
$36 | - | |
06 | 2.2511: Insulate bare equipment | $802 | $930 | - | - |
$802
-
MMBtu
|
|
07 | 2.6211: Conserve energy by efficient use of vending machines | $200 | $312 |
$193
2,496
kWh
|
$7 | - | |
TOTAL RECOMMENDED | $26,528 | $14,378 |
$20,386
263,700
kWh
|
$774 |
$5,368
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,861 | $1,390 |
$8,955
115,836
kWh
|
$340 |
$4,566
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs