| Assessment Year | 2008 |
|---|---|
| Principal Product | Sheet metal parts |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 76 |
| Plant Area |
66,455
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 4,590
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $168,594 | 1,962,760 |
kWh
|
$0.086 |
| Electricity Fees | $5,684 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,232 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $769 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $40,254 | $14,080 |
$38,968
451,337
kWh
|
$1,286 | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $4,189 | $722 |
$4,055
46,965
kWh
|
$134 | - | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,965 | $7,500 |
$1,902
22,032
kWh
|
$63 | - | |
| 04 | 2.6211: Conserve energy by efficient use of vending machines | $779 | $775 |
$754
8,736
kWh
|
$25 | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $589 | $150 |
$570
6,598
kWh
|
$19 | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $276 | $231 |
$267
3,098
kWh
|
$9 | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $180 | $105 |
$86
999
kWh
|
$3 | $91 | |
| TOTAL RECOMMENDED | $48,232 | $23,563 |
$46,602
539,765
kWh
|
$1,539 | $91 | ||
| TOTAL IMPLEMENTED | $769 | $255 |
$656
7,597
kWh
|
$22 | $91 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs