Assessment Year | 2008 |
---|---|
Principal Product | Tires |
NAICS | 326211: Tire Manufacturing (except Retreading) |
SIC | 3011: Tires and Inner Tubes |
Sales Range | $50 M to 100M |
# of Employees | 1,550 |
Plant Area |
1,918,000
ft2
|
Annual Production | 9,500,000
pieces
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $5,201,937 | 148,684,000 |
kWh
|
$0.035 |
Electricity Demand | $1,277,437 | 254,735 |
kW-mo/yr
|
$5.01 |
Electricity Fees | $258,457 | - |
|
- |
Natural Gas | $4,091,142 | 590,191 |
MMBtu
|
$6.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $469,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $385,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $274,767 | $187,520 |
$264,199
7,550,692
kWh
|
- | $10,568 | - | - | |
02 | 2.2135: Repair and eliminate steam leaks | $110,300 | $3,650 | - | - | - |
$110,300
-
MMBtu
|
- | |
03 | 2.1213: Direct warmest air to combustion intake | $47,583 | $1,290 | - | - | - |
$47,583
-
MMBtu
|
- | |
04 | 4.611: Begin a practice of predictive / preventative maintenance | $21,390 | $11,905 | - | - | - | - | $21,390 | |
05 | 2.2511: Insulate bare equipment | $7,830 | $1,940 | - | - | - |
$7,830
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,497 | $3,500 |
$1,165
33,288
kWh
|
$240
-
kW-mo/yr
|
$56 | - | $3,036 | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,820 | $1,710 |
$1,119
31,980
kWh
|
$631
-
kW-mo/yr
|
$70 | - | - | |
08 | 2.6211: Conserve energy by efficient use of vending machines | $572 | $1,402 |
$550
15,725
kWh
|
- | $22 | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $333 | $165 | - | - | - |
$333
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $469,092 | $213,082 |
$267,033
7,631,685
kWh
|
$871
-
kW-mo/yr
|
$10,716 |
$166,046
-
MMBtu
|
$24,426 | ||
TOTAL IMPLEMENTED | $385,400 | $191,335 |
$264,199
7,550,692
kWh
|
- | $10,568 |
$110,633
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs