ITAC Assessment: LL0227
ITAC logo
ITAC Assessment: LL0227
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Rice Drying
NAICS 311212: Rice Milling
SIC 2044: Rice Milling
Sales Range $500
k
to 1
M
# of Employees 16
Plant Area 50,000
ft2
Annual Production 13,364,000
lb
Production Hrs. Annual 3,984
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $64,924 691,635
kWh
Electricity Demand $9,940 1,473
kW-mo/yr
Electricity Fees $2,850 -
Natural Gas $43,465 3,515
MMBtu
Other Gas $17,631 1,376
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,016 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,760

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.2511: Insulate bare equipment $24,360 - - - - $13,899
-
MMBtu
$10,461
-
MMBtu
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,515 $2,800 $9,167
97,654
kWh
- $348 - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,336 $2,600 $5,017
53,446
kWh
$1,087
-
kW-mo/yr
$232 - - - -
04 2.7134: Use photocell controls $1,045 - $1,007
10,728
kWh
- $38 - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $944 $150 - - - $944
-
MMBtu
- - -
06 2.7135: Install occupancy sensors $851 - $820
8,735
kWh
- $31 - - - -
07 2.8114: Change rate schedules or other changes in utility service $465 - - - $465 - - - -
08 4.611: Begin a practice of predictive / preventative maintenance $5,500 $250 - - - - - $1,500 $4,000
TOTAL RECOMMENDED $49,016 $5,800 $16,011
170,563
kWh
$1,087
-
kW-mo/yr
$1,114 $14,843
-
MMBtu
$10,461
-
MMBtu
$1,500 $4,000
TOTAL IMPLEMENTED $22,760 $5,800 $14,184
151,100
kWh
$1,087
-
kW-mo/yr
$1,045 $944
-
MMBtu
- $1,500 $4,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs