| Assessment Year | 2005 |
|---|---|
| Principal Product | Rice Milling |
| NAICS | 311211: Flour Milling |
| SIC | 2044: Rice Milling |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
112,000
ft2
|
| Annual Production | 2,250,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $40,852 | 760,474 |
kWh
|
$0.054 |
| Electricity Demand | $29,815 | 4,253 |
kW-mo/yr
|
$7.01 |
| Electricity Fees | $2,684 | - |
|
- |
| Natural Gas | $50,775 | 5,252 |
MMBtu
|
$9.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $181,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $177,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,146 | $2,000 |
$12,436
231,490
kWh
|
$3,119
-
kW-mo/yr
|
$591 | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,111 | $50 |
$2,997
55,789
kWh
|
- | $114 | - | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,676 | $400 |
$2,580
48,022
kWh
|
- | $96 | - | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,991 | - | - | - | - |
$1,991
-
MMBtu
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,445 | - |
$1,392
25,907
kWh
|
- | $53 | - | - | - | |
| 06 | 2.7134: Use photocell controls | $1,100 | - |
$1,060
19,727
kWh
|
- | $40 | - | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $667 | $150 | - | - | - |
$667
-
MMBtu
|
- | - | |
| 08 | 4.611: Begin a practice of predictive / preventative maintenance | $154,500 | $2,500 | - | - | - | - | $152,000 | $2,500 | |
| TOTAL RECOMMENDED | $181,636 | $5,100 |
$20,465
380,935
kWh
|
$3,119
-
kW-mo/yr
|
$894 |
$2,658
-
MMBtu
|
$152,000 | $2,500 | ||
| TOTAL IMPLEMENTED | $177,100 | $5,100 |
$18,013
335,301
kWh
|
$3,119
-
kW-mo/yr
|
$801 |
$667
-
MMBtu
|
$152,000 | $2,500 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs