Assessment Year | 2005 |
---|---|
Principal Product | Rice milling |
NAICS | 311212: Rice Milling |
SIC | 2044: Rice Milling |
Sales Range | $10 M to 50M |
# of Employees | 38 |
Plant Area |
32,000
ft2
|
Annual Production | 36,895
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,751 | 1,340,186 |
kWh
|
$0.048 |
Electricity Demand | $32,680 | 4,327 |
kW-mo/yr
|
$7.55 |
Electricity Fees | $3,772 | - |
|
- |
Natural Gas | $1,689 | 128 |
MMBtu
|
$13.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,945 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,781 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,226 | $1,500 |
$4,067
84,172
kWh
|
$159 | - | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $2,767 | - |
$2,663
55,110
kWh
|
$104 | - | - | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $726 | - | - | - |
$726
-
MMBtu
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $685 | $250 |
$659
13,629
kWh
|
$26 | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $645 | - |
$621
12,853
kWh
|
$24 | - | - | - | |
06 | 2.7135: Install occupancy sensors | $26 | - |
$25
523
kWh
|
$1 | - | - | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $31,870 | $800 | - | - | - | $29,370 | $2,500 | |
TOTAL RECOMMENDED | $40,945 | $2,550 |
$8,035
166,287
kWh
|
$314 |
$726
-
MMBtu
|
$29,370 | $2,500 | ||
TOTAL IMPLEMENTED | $36,781 | $2,550 |
$4,726
97,801
kWh
|
$185 | - | $29,370 | $2,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs