ITAC Assessment: LL0220
ITAC logo
ITAC Assessment: LL0220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Rice milling
NAICS 311212: Rice Milling
SIC 2044: Rice Milling
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 30,000
ft2
Annual Production 4,500
ton
Production Hrs. Annual 2,250
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $181,477 1,260,030
kWh
Electricity Fees $6,115 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,384 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $13,379 $4,500 $12,939
89,838
kWh
$440 -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,475 $1,600 $4,328
30,051
kWh
$147 -
03 2.7224: Reduce space conditioning during non-working hours $3,929 $169 $3,800
26,381
kWh
$129 -
04 2.4239: Eliminate or reduce compressed air usage $3,170 $716 $3,066
21,284
kWh
$104 -
05 2.7111: Reduce illumination to minimum necessary levels $3,082 $435 $2,981
20,696
kWh
$101 -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $6,179 $5,580 $5,976
41,492
kWh
$203 -
07 2.4231: Reduce the pressure of compressed air to the minimum required $2,732 $30 $2,642
18,342
kWh
$90 -
08 2.7135: Install occupancy sensors $1,240 $360 $1,199
8,326
kWh
$41 -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,198 $525 $719
4,993
kWh
$24 $455
TOTAL RECOMMENDED $39,384 $13,915 $37,650
261,403
kWh
$1,279 $455
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs