ITAC Assessment: LL0207
ITAC logo
ITAC Assessment: LL0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Chocolate Beverages
NAICS 311511: Fluid Milk Manufacturing
SIC 2020:
Sales Range $10
M
to 50
M
# of Employees 46
Plant Area 75,000
ft2
Annual Production 48,895,560
pieces
Production Hrs. Annual 6,732
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,828 1,241,200
kWh
Electricity Demand $29,241 3,841
kW-mo/yr
Electricity Fees $3,443 -
Natural Gas $336,926 41,751
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $142,735 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,251

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
01 2.2441: Preheat boiler makeup water with waste process heat $36,769 $16,000 - - - $36,769
-
MMBtu
- - -
02 2.2511: Insulate bare equipment $34,833 $7,488 - - - $34,833
-
MMBtu
- - -
03 2.2121: Increase amount of condensate returned $6,837 $12,236 - - - $6,170
-
MMBtu
- $667
-
Tgal
-
04 2.7111: Reduce illumination to minimum necessary levels $3,171 $225 $2,428
51,218
kWh
$624
-
kW-mo/yr
$119 - - - -
05 2.2135: Repair and eliminate steam leaks $2,149 $1,960 - - - $2,149
-
MMBtu
- - -
06 2.7134: Use photocell controls $449 $30 $432
9,105
kWh
- $17 - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $701 $525 $237
4,993
kWh
- $9 - $455 - -
08 2.7135: Install occupancy sensors $99 $120 $95
2,003
kWh
- $4 - - - -
09 2.7132: Install timers on light switches in little used areas $33 $180 $32
674
kWh
- $1 - - - -
10 4.611: Begin a practice of predictive / preventative maintenance $46,500 $3,150 - - - - $44,000 - $2,500
11 3.4115: Recover and reuse cooling water $11,194 $32,000 - - - - - $11,194
-
Tgal
-
TOTAL RECOMMENDED $142,735 $73,914 $3,224
67,993
kWh
$624
-
kW-mo/yr
$150 $79,921
-
MMBtu
$44,455 $11,861
-
Tgal
$2,500
TOTAL IMPLEMENTED $120,251 $28,598 - - - $73,751
-
MMBtu
$44,000 - $2,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs