Assessment Year | 2004 |
---|---|
Principal Product | boat/repair |
NAICS | 336611: Ship Building and Repairing |
SIC | 3731: Ship Building and Repairing |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
250,000
ft2
|
Annual Production | 150
pieces
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $400,044 | 6,095,173 |
kWh
|
$0.066 |
Electricity Demand | $6,616 | 1,867 |
kW-mo/yr
|
$3.54 |
Electricity Fees | $29,466 | - |
|
- |
Natural Gas | $31,419 | 3,566 |
MMBtu
|
$8.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,135 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $23,139 | $810 |
$19,107
291,133
kWh
|
$2,478
-
kW-mo/yr
|
$1,554 | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $14,598 | $11,757 |
$13,618
207,492
kWh
|
- | $980 | - | - | |
03 | 2.7135: Install occupancy sensors | $10,904 | $960 |
$10,172
154,989
kWh
|
- | $732 | - | - | |
04 | 2.7134: Use photocell controls | $8,001 | $420 |
$7,464
113,724
kWh
|
- | $537 | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,518 | $30 |
$7,013
106,852
kWh
|
- | $505 | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,239 | $2,120 |
$4,887
74,456
kWh
|
- | $352 | - | - | |
07 | 2.2511: Insulate bare equipment | $1,683 | $1,770 | - | - | - |
$1,683
-
MMBtu
|
- | |
08 | 4.611: Begin a practice of predictive / preventative maintenance | $2,500 | $60 | - | - | - | - | $2,500 | |
09 | 4.611: Begin a practice of predictive / preventative maintenance | $2,055 | $2,878 | - | - | - | - | $2,055 | |
TOTAL RECOMMENDED | $75,637 | $20,805 |
$62,261
948,646
kWh
|
$2,478
-
kW-mo/yr
|
$4,660 |
$1,683
-
MMBtu
|
$4,555 | ||
TOTAL IMPLEMENTED | $50,135 | $8,088 |
$38,471
586,165
kWh
|
$2,478
-
kW-mo/yr
|
$2,948 |
$1,683
-
MMBtu
|
$4,555 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs