Assessment Year | 2004 |
---|---|
Principal Product | Oil and Gas field equipment |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
45,000
ft2
|
Annual Production | 24
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $95,339 | 1,725,289 |
kWh
|
$0.055 |
Electricity Demand | $32,130 | 5,691 |
kW-mo/yr
|
$5.65 |
Electricity Fees | $10,548 | - |
|
- |
Natural Gas | $60,436 | 9,363 |
MMBtu
|
$6.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,346 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,447 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7131: Add area lighting switches | $37,447 | $4,522 | - | - | - |
$37,447
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $24,382 | $3,930 |
$22,513
407,400
kWh
|
- | $1,869 | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $8,505 | $575 |
$6,565
118,797
kWh
|
$1,288
-
kW-mo/yr
|
$652 | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,939 | $2,840 |
$3,637
65,823
kWh
|
- | $302 | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,428 | $30 |
$2,148
38,876
kWh
|
$1,017
-
kW-mo/yr
|
$263 | - | - | |
06 | 2.7132: Install timers on light switches in little used areas | $1,554 | $480 |
$1,435
25,965
kWh
|
- | $119 | - | - | |
07 | 2.7134: Use photocell controls | $1,473 | $510 |
$1,360
24,619
kWh
|
- | $113 | - | - | |
08 | 2.7132: Install timers on light switches in little used areas | $1,118 | $48 |
$1,032
18,670
kWh
|
- | $86 | - | - | |
09 | 4.611: Begin a practice of predictive / preventative maintenance | $2,500 | $60 | - | - | - | - | $2,500 | |
TOTAL RECOMMENDED | $84,346 | $12,995 |
$38,690
700,150
kWh
|
$2,305
-
kW-mo/yr
|
$3,404 |
$37,447
-
MMBtu
|
$2,500 | ||
TOTAL IMPLEMENTED | $37,447 | $4,522 | - | - | - |
$37,447
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs