ITAC Assessment: LL0175
ITAC logo
ITAC Assessment: LL0175
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Structural and Architectural Metals
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 100,000
ft2
Annual Production 7,000
ton
Production Hrs. Annual 2,600
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,869 1,510,312
kWh
Electricity Demand $39,351 7,002
kW-mo/yr
Electricity Fees $7,712 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,280 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Personnel Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $9,977 $945 $5,835
108,975
kWh
$3,541
-
kW-mo/yr
$601 - -
02 2.7134: Use photocell controls $3,273 $280 $1,918
35,818
kWh
$1,158
-
kW-mo/yr
$197 - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,190 $15 $1,277
23,855
kWh
$781
-
kW-mo/yr
$132 - -
04 2.7135: Install occupancy sensors $746 $56 $437
8,162
kWh
$264
-
kW-mo/yr
$45 - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $594 $800 $558
10,428
kWh
- $36 - -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $40,875 $100,279 - - - $40,875
-
gal
-
07 2.8112: Combine utility meters $1,625 - - - - - $1,625
TOTAL RECOMMENDED $59,280 $102,375 $10,025
187,238
kWh
$5,744
-
kW-mo/yr
$1,011 $40,875
-
gal
$1,625
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs