ITAC Assessment: LL0163
ITAC logo
ITAC Assessment: LL0163
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Childrens clothing
NAICS 315280: Other Cut and Sew Apparel Manufacturing
SIC 2329: Men's and Boys' Clothing, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 205
Plant Area 66,000
ft2
Annual Production 7,320,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,439 1,598,625
kWh
Electricity Demand $18,300 5,689
kW-mo/yr
Electricity Fees $4,219 -
Natural Gas $1,907 243
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,258 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,982 $2,560 $2,867
52,006
kWh
- $115 -
02 2.7111: Reduce illumination to minimum necessary levels $1,665 $690 $1,392
25,252
kWh
$209
-
kW-mo/yr
$64 -
03 2.4231: Reduce the pressure of compressed air to the minimum required $479 $20 $339
6,149
kWh
$122
-
kW-mo/yr
$18 -
04 2.7135: Install occupancy sensors $182 $104 $130
2,358
kWh
$45
-
kW-mo/yr
$7 -
05 3.5313: Increase amount of waste recovered for resale $4,950 - - - - $4,950
-
lb
TOTAL RECOMMENDED $10,258 $3,374 $4,728
85,765
kWh
$376
-
kW-mo/yr
$204 $4,950
-
lb
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs