ITAC Assessment: LL0160
ITAC logo
ITAC Assessment: LL0160
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Oilfield Equipment
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 70,000
ft2
Annual Production 21,000
pieces
Production Hrs. Annual 5,824
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $296,629 4,492,372
kWh
Electricity Demand $4,788 848
kW-mo/yr
Electricity Fees $13,592 -
Natural Gas $23,058 5,685
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $98,092 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
01 2.7134: Use photocell controls $50,631 $4,551 $48,684
736,969
kWh
- $1,947 - - -
02 2.7135: Install occupancy sensors $17,563 $5,075 $16,890
255,673
kWh
- $673 - - -
03 2.7232: Replace existing hvac unit with high efficiency model $4,307 $10,605 - - - $4,307
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,909 $1,360 $4,721
71,463
kWh
- $188 - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,798 $900 $660
9,986
kWh
$79
-
kW-mo/yr
$30 - - $1,029
06 2.8112: Combine utility meters $15,037 - - - $15,037 - - -
07 4.611: Begin a practice of predictive / preventative maintenance $1,928 $786 - - - - - $1,928
08 2.8112: Combine utility meters $1,163 - - - - - $1,163
-
Tgal
-
09 2.8112: Combine utility meters $756 - - - - $756
-
MMBtu
- -
TOTAL RECOMMENDED $98,092 $23,277 $70,955
1,074,091
kWh
$79
-
kW-mo/yr
$17,875 $5,063
-
MMBtu
$1,163
-
Tgal
$2,957
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs