Assessment Year | 2003 |
---|---|
Principal Product | Spray drying |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $1 M to 5M |
# of Employees | 12 |
Plant Area |
31,800
ft2
|
Annual Production | 1,786,101
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,443 | 1,654,400 |
kWh
|
$0.061 |
Electricity Demand | $1,200 | 5,328 |
kW-mo/yr
|
$0.23 |
Electricity Fees | $3,964 | - |
|
- |
Natural Gas | $88,461 | 21,759 |
MMBtu
|
$4.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,632 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $32,145 | $11,600 |
$30,909
489,834
kWh
|
- | $1,236 | - | - | |
02 | 2.7134: Use photocell controls | $16,687 | $2,262 |
$15,962
262,919
kWh
|
$83
-
kW-mo/yr
|
$642 | - | - | |
03 | 2.4235: Remove or close off unneeded compressed air lines | $16,068 | $5,800 |
$15,450
244,857
kWh
|
- | $618 | - | - | |
04 | 2.7135: Install occupancy sensors | $1,303 | $164 |
$1,249
20,568
kWh
|
$4
-
kW-mo/yr
|
$50 | - | - | |
05 | 3.4156: Use flow control valves on equipment to optimize water use | $116 | $226 | - | - | - |
$116
-
Tgal
|
- | |
06 | 4.513: Re-arrange equipment layout to reduce labor costs | $5,000 | $420 | - | - | - | - | $5,000 | |
TOTAL RECOMMENDED | $71,319 | $20,472 |
$63,570
1,018,178
kWh
|
$87
-
kW-mo/yr
|
$2,546 |
$116
-
Tgal
|
$5,000 | ||
TOTAL IMPLEMENTED | $54,632 | $18,210 |
$47,608
755,259
kWh
|
$4
-
kW-mo/yr
|
$1,904 |
$116
-
Tgal
|
$5,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs