| Assessment Year | 2002 |
|---|---|
| Principal Product | Oilfiled Tools |
| NAICS |
n/a
|
| SIC | 3533: Oil and Gas Field Machinery and Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 240 |
| Plant Area |
180,000
ft2
|
| Annual Production | 6,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $164,912 | 4,499,348 |
kWh
|
$0.037 |
| Electricity Demand | $71,618 | 9,744 |
kW-mo/yr
|
$7.35 |
| Electricity Fees | $935 | - |
|
- |
| Natural Gas | $169,532 | 31,300 |
MMBtu
|
$5.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $101,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $70,544 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,605 | $4,350 |
$15,005
412,688
kWh
|
- | $600 | - | - | - | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $15,140 | $4,600 | - | - | - |
$15,140
-
MMBtu
|
- | - | |
| 03 | 2.7134: Use photocell controls | $10,108 | $1,092 |
$5,456
150,050
kWh
|
$4,263
-
kW-mo/yr
|
$389 | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $5,710 | $494 |
$4,299
118,223
kWh
|
$1,191
-
kW-mo/yr
|
$220 | - | - | - | |
| 05 | 2.1134: Eliminate leaks in combustible gas lines | $3,410 | $1,240 | - | - | - |
$3,410
-
MMBtu
|
- | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $1,284 | $180 |
$869
23,902
kWh
|
$366
-
kW-mo/yr
|
$49 | - | - | - | |
| 07 | 3.5111: Filter and reuse hydraulic oil | $40,689 | $8,000 | - | - | - | - |
$40,689
-
gal
|
- | |
| 08 | 4.611: Begin a practice of predictive / preventative maintenance | $9,556 | $12,425 | - | - | - | - | - | $9,556 | |
| TOTAL RECOMMENDED | $101,502 | $32,381 |
$25,629
704,863
kWh
|
$5,820
-
kW-mo/yr
|
$1,258 |
$18,550
-
MMBtu
|
$40,689
-
gal
|
$9,556 | ||
| TOTAL IMPLEMENTED | $70,544 | $26,195 |
$15,874
436,590
kWh
|
$366
-
kW-mo/yr
|
$649 |
$3,410
-
MMBtu
|
$40,689
-
gal
|
$9,556 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs