| Assessment Year | 2002 |
|---|---|
| Principal Product | Hot sauces and peppers |
| NAICS |
n/a
|
| SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
6,500
ft2
|
| Annual Production | 25,000,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,178 | 656,285 |
kWh
|
$0.054 |
| Electricity Demand | $27,256 | 3,610 |
kW-mo/yr
|
$7.55 |
| Electricity Fees | $2,497 | - |
|
- |
| Natural Gas | $23,796 | 4,407 |
MMBtu
|
$5.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,278 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,518 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,787 | $435 |
$3,641
68,248
kWh
|
- | $146 | - | - | |
| 02 | 2.3212: Optimize plant power factor | $2,835 | $3,325 | - |
$2,726
-
kW-mo/yr
|
$109 | - | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $2,243 | $4,465 | - | - | - |
$2,243
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $457 | $754 | - | - | - |
$457
-
MMBtu
|
- | |
| 05 | 2.2511: Insulate bare equipment | $225 | $378 | - | - | - |
$225
-
MMBtu
|
- | |
| 06 | 2.8114: Change rate schedules or other changes in utility service | $9,786 | - | - | - | - | - |
$9,786
-
Tgal
|
|
| 07 | 2.8123: Pay utility bills on time | $945 | - | - | - | - | - |
$945
-
Tgal
|
|
| TOTAL RECOMMENDED | $20,278 | $9,357 |
$3,641
68,248
kWh
|
$2,726
-
kW-mo/yr
|
$255 |
$2,925
-
MMBtu
|
$10,731
-
Tgal
|
||
| TOTAL IMPLEMENTED | $14,518 | $435 |
$3,641
68,248
kWh
|
- | $146 | - |
$10,731
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs