| Assessment Year | 2001 |
|---|---|
| Principal Product | Steel Fabrication |
| NAICS |
n/a
|
| SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
| Sales Range | $100 M to 500M |
| # of Employees | 100 |
| Plant Area |
79,000
ft2
|
| Annual Production | 120
pieces
|
| Production Hrs. Annual | 6,917
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $65,635 | 1,551,750 |
kWh
|
$0.042 |
| Electricity Demand | $45,730 | 5,775 |
kW-mo/yr
|
$7.92 |
| Electricity Fees | $4,148 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,655 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,797 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $605 | $74 |
$416
51,057
kWh
|
$166
-
kW-mo/yr
|
$23 | - | - | |
| 02 | 2.3212: Optimize plant power factor | $9,873 | $10,440 | - |
$9,493
-
kW-mo/yr
|
$380 | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,253 | - |
$201
24,647
kWh
|
$1,004
-
kW-mo/yr
|
$48 | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,892 | $2,400 |
$12,396
1,522,808
kWh
|
- | $496 | - | - | |
| 05 | 3.5311: Recover and reuse waste material | $552 | - | - | - | - | - |
$552
-
lb
|
|
| 06 | 2.8114: Change rate schedules or other changes in utility service | $1,480 | - | - | - | - |
$1,480
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $26,655 | $12,914 |
$13,013
1,598,512
kWh
|
$10,663
-
kW-mo/yr
|
$947 |
$1,480
-
Tgal
|
$552
-
lb
|
||
| TOTAL IMPLEMENTED | $24,797 | $12,840 |
$12,396
1,522,808
kWh
|
$9,493
-
kW-mo/yr
|
$876 |
$1,480
-
Tgal
|
$552
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs