Assessment Year | 2001 |
---|---|
Principal Product | Offshore drilling completion equipment |
NAICS |
n/a
|
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 94 |
Plant Area |
45,600
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $193,878 | 2,506,650 |
kWh
|
$0.077 |
Electricity Demand | $41,672 | 7,392 |
kW-mo/yr
|
$5.64 |
Electricity Fees | $(-28,338.0) | - |
|
- |
Natural Gas | $7,004 | 598 |
MMBtu
|
$11.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,858 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,588 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,070 | $8,640 | - |
$5,837
-
kW-mo/yr
|
$233 | - | - | |
02 | 2.7134: Use photocell controls | $6,866 | $325 |
$4,854
67,392
kWh
|
$1,748
-
kW-mo/yr
|
$264 | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $5,657 | $82 |
$4,450
61,776
kWh
|
$989
-
kW-mo/yr
|
$218 | - | - | |
04 | 2.4321: Upgrade obsolete equipment | $441 | $180 |
$424
5,887
kWh
|
- | $17 | - | - | |
05 | 2.8123: Pay utility bills on time | $296 | - | - | - | $296 | - | - | |
06 | 3.5313: Increase amount of waste recovered for resale | $18,851 | - | - | - | - | - |
$18,851
-
lb
|
|
07 | 3.4133: Clean fouling from water lines regularly | $9,677 | $2,200 | - | - | - |
$9,677
-
Tgal
|
- | |
TOTAL RECOMMENDED | $47,858 | $11,427 |
$9,728
135,055
kWh
|
$8,574
-
kW-mo/yr
|
$1,028 |
$9,677
-
Tgal
|
$18,851
-
lb
|
||
TOTAL IMPLEMENTED | $19,588 | $180 |
$424
5,887
kWh
|
- | $313 | - |
$18,851
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs