ITAC Assessment: LE0618
ITAC logo
ITAC Assessment: LE0618
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Co-Packing Boxes
NAICS 493110: General Warehousing and Storage
SIC 4225: General Warehousing and Storage
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 371,559
ft2
Annual Production 18,000,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,980 875,189
kWh
Electricity Demand $27,967 2,542
kW-mo/yr
Natural Gas $143,184 13,504
MMBtu
Waste Disposal Costs
Water Usage $43,269 21,092
Tgal
Water Disposal $51,443 18,983
Tgal
TOTAL YEARLY COSTS $360,843
RECOMMENDED SAVINGS* $70,910 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $780 - $490
4,488
kWh
$290
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,047 $1,612 $673
6,170
kWh
$374
-
kW-mo/yr
- - -
03 2.1321: Replace fossil fuel equipment with electrical equipment $69,083 $309,960 $(-7,557.0)
(-69,333)
kWh
- $58,240
-
MMBtu
$(-9,600.0) $28,000
TOTAL RECOMMENDED $70,910 $311,572 $(-6,394.0)
(-58,675)
kWh
$664
-
kW-mo/yr
$58,240
-
MMBtu
$(-9,600.0) $28,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs