Assessment Year | 2024 |
---|---|
Principal Product | Flavoring Extracts and Flavoring Syrups |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 60 |
Plant Area |
155,474
ft2
|
Annual Production | 12,035
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $447,708 | 6,903,967 |
kWh
|
$0.065 |
Electricity Demand | $87,641 | 14,291 |
kW-mo/yr
|
$6.13 |
Electricity Fees | $122,226 | - |
|
- |
Natural Gas | $163,730 | 46,002 |
MMBtu
|
$3.56 |
TOTAL YEARLY COSTS | $821,305 | |||
RECOMMENDED SAVINGS* | $115,089 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,555 | $510 |
$1,555
23,924
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,704 | $2,300 |
$1,443
22,209
kWh
|
$261
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,383 | $5,000 |
$1,813
27,900
kWh
|
$570
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,804 | $49,222 |
$10,589
162,913
kWh
|
$2,215
-
kW-mo/yr
|
- | - | |
05 | 2.1224: Replace boiler | $96,643 | $400,000 | - | - |
$66,643
-
MMBtu
|
$30,000 | |
TOTAL RECOMMENDED | $115,089 | $457,032 |
$15,400
236,946
kWh
|
$3,046
-
kW-mo/yr
|
$66,643
-
MMBtu
|
$30,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs