Assessment Year | 2022 |
---|---|
Principal Product | Mechanical Assemblies |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
120,000
ft2
|
Annual Production | 15,000
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $32,593 | 544,116 |
kWh
|
$0.060 | |
Electricity Demand | $15,906 | 1,865 |
kW-mo/yr
|
$8.53 | |
Electricity Fees | $8,329 | - |
|
- | |
LPG | $32,390 | 1,564 |
MMBtu
|
$20.71 | |
Fuel Oil #2 | $7,333 | 357 |
MMBtu
|
$20.54 | |
Waste Disposal Costs | |||||
Water Usage | $11,111 | 597 |
Tgal
|
$18.62 | |
TOTAL YEARLY COSTS | $107,662 | ||||
RECOMMENDED SAVINGS* | $62,858 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,161 | $4,100 | - | - |
$6,161
-
MMBtu
|
- | - | |
02 | 2.7231: Use radiant heater for spot heating | $3,206 | $3,500 | - | - | - |
$3,206
-
MMBtu
|
- | |
03 | 4.652: Replace existing equipment with more suitable substitutes | $21,231 | $50,000 | - | - | - | - | $21,231 | |
04 | 2.1331: Burn a less expensive grade of fuel | $24,359 | $62,500 | - | - | - | - | $24,359 | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $5,998 | $18,621 | - | - |
$5,998
-
MMBtu
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,903 | $6,154 |
$1,394
23,275
kWh
|
$509
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $62,858 | $144,875 |
$1,394
23,275
kWh
|
$509
-
kW-mo/yr
|
$12,159
-
MMBtu
|
$3,206
-
MMBtu
|
$45,590 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs