ITAC Assessment: LE0526
ITAC logo
ITAC Assessment: LE0526
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Machined Parts
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 5
Plant Area 23,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 6,708
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,663 533,060
kWh
Electricity Demand $8,241 2,161
kW-mo/yr
Electricity Fees $20,576 -
Natural Gas $3,777 332
MMBtu
TOTAL YEARLY COSTS $100,257
RECOMMENDED SAVINGS* $76,206 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,392

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.8123: Pay utility bills on time $671 - - - $671 -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,267 $1,927 $6,897
54,309
kWh
$370
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,461 $2,205 $6,187
48,718
kWh
$274
-
kW-mo/yr
- -
04 2.2443: Re-use or recycle hot or cold process exhaust air $1,817 $1,200 $1,817
14,310
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,717 $1,900 $520
4,090
kWh
$1,197
-
kW-mo/yr
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,615 $3,540 $1,531
12,054
kWh
$84
-
kW-mo/yr
- -
07 2.4221: Install compressor air intakes in coolest locations $728 $1,800 $690
5,431
kWh
$38
-
kW-mo/yr
- -
08 2.7232: Replace existing hvac unit with high efficiency model $18,661 $48,235 $17,891
140,868
kWh
$770
-
kW-mo/yr
- -
09 2.3513: Consider power loss as well as initial loads and load growth in down-sizing transformers $37,269 $125,000 - - - $37,269
TOTAL RECOMMENDED $76,206 $185,807 $35,533
279,780
kWh
$2,733
-
kW-mo/yr
$671 $37,269
TOTAL IMPLEMENTED $36,392 $57,807 $33,026
260,039
kWh
$2,695
-
kW-mo/yr
$671 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs