Assessment Year | 2021 |
---|---|
Principal Product | Surfactants |
NAICS | 325611: Soap and Other Detergent Manufacturing |
SIC | 2841: Soap and Other Detergents, Except Specialty Cleaners |
Sales Range | $10 M to 50M |
# of Employees | 39 |
Plant Area |
130,000
ft2
|
Annual Production | 186,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,263,418 | 15,743,391 |
kWh
|
$0.080 |
Electricity Demand | $60,550 | 27,999 |
kW-mo/yr
|
$2.16 |
Electricity Fees | $149,912 | - |
|
- |
Natural Gas | $728,880 | 139,722 |
MMBtu
|
$5.22 |
TOTAL YEARLY COSTS | $2,202,760 | |||
RECOMMENDED SAVINGS* | $308,099 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $256,384 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $72,824 | $26,000 | - | - |
$72,824
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,651 | $10,100 |
$16,172
202,149
kWh
|
$479
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $39,439 | $31,000 |
$38,029
475,362
kWh
|
$1,410
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $62,020 | $55,000 |
$59,804
747,544
kWh
|
$2,216
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,327 | $20,855 |
$16,707
208,834
kWh
|
$620
-
kW-mo/yr
|
- | |
06 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $48,123 | $90,000 | - | - |
$48,123
-
MMBtu
|
|
07 | 2.2441: Preheat boiler makeup water with waste process heat | $51,715 | $200,000 | - | - |
$51,715
-
MMBtu
|
|
TOTAL RECOMMENDED | $308,099 | $432,955 |
$130,712
1,633,889
kWh
|
$4,725
-
kW-mo/yr
|
$172,662
-
MMBtu
|
||
TOTAL IMPLEMENTED | $256,384 | $232,955 |
$130,712
1,633,889
kWh
|
$4,725
-
kW-mo/yr
|
$120,947
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs