Assessment Year | 2019 |
---|---|
Principal Product | Flexible Packaging |
NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $100 M to 500M |
# of Employees | 123 |
Plant Area |
250,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,133,586 | 20,193,600 |
kWh
|
$0.056 |
Electricity Demand | $101,940 | 40,026 |
kW-mo/yr
|
$2.55 |
Electricity Fees | $28,968 | - |
|
- |
Natural Gas | $523,324 | 122,764 |
MMBtu
|
$4.26 |
TOTAL YEARLY COSTS | $1,787,818 | |||
RECOMMENDED SAVINGS* | $352,427 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8123: Pay utility bills on time | $4,000 | - | - | - | $4,000 | |
02 | 3.1194: Use automatic flow control | $20,000 | $6,500 | - | - | $20,000 | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $25,833 | $35,000 |
$24,602
439,316
kWh
|
$1,231
-
kW-mo/yr
|
- | |
04 | 2.4226: Use / purchase optimum sized compressor | $10,332 | $25,000 |
$8,792
156,994
kWh
|
$1,540
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,769 | $115,000 |
$21,627
386,190
kWh
|
$2,142
-
kW-mo/yr
|
- | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $268,493 | $1,534,575 |
$252,688
4,512,293
kWh
|
$15,805
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $352,427 | $1,716,075 |
$307,709
5,494,793
kWh
|
$20,718
-
kW-mo/yr
|
$24,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs