ITAC Assessment: LE0469
ITAC logo
ITAC Assessment: LE0469
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Paper products
NAICS 322230: Stationery Product Manufacturing
SIC 2752: Commercial Printing, Lithographic
Sales Range $50
M
to 100
M
# of Employees 35
Plant Area 130,000
ft2
Annual Production 13,000
units
Production Hrs. Annual 6,240
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,945 986,839
kWh
Electricity Demand $33,600 4,450
kW-mo/yr
Electricity Fees $18,755 -
Natural Gas $28,391 3,047
MMBtu
TOTAL YEARLY COSTS $130,691
RECOMMENDED SAVINGS* $40,135 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,507 $1,000 $4,285
84,055
kWh
$1,222
-
kW-mo/yr
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $159 $175 $114
2,234
kWh
$45
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $5,321 $6,000 - - $5,321
-
MMBtu
04 2.7232: Replace existing hvac unit with high efficiency model $18,723 $23,000 $17,905
351,086
kWh
$818
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $10,425 $18,125 $8,115
159,120
kWh
$2,310
-
kW-mo/yr
-
TOTAL RECOMMENDED $40,135 $48,300 $30,419
596,495
kWh
$4,395
-
kW-mo/yr
$5,321
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs