ITAC Assessment: LE0466
ITAC logo
ITAC Assessment: LE0466
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Animal formula
NAICS 339999: All Other Miscellaneous Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 20
Plant Area 200,000
ft2
Annual Production 2,000,000
ton
Production Hrs. Annual 4,992
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,357 772,794
kWh
Electricity Demand $21,302 4,169
kW-mo/yr
Electricity Fees $11,643 -
Natural Gas $46,388 12,557
MMBtu
LPG $111,180 8,894
MMBtu
TOTAL YEARLY COSTS $236,870
RECOMMENDED SAVINGS* $60,798 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $482 $40 $416
6,927
kWh
$66
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,835 $750 $35
580
kWh
$2,800
-
kW-mo/yr
- - -
03 2.1331: Burn a less expensive grade of fuel $53,204 $20,000 - - $(-16,236.0)
-
MMBtu
$55,000
-
MMBtu
$14,440
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $158 $180 $133
2,211
kWh
$25
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,119 $7,950 $3,690
61,501
kWh
$429
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $60,798 $28,920 $4,274
71,219
kWh
$3,320
-
kW-mo/yr
$(-16,236.0)
-
MMBtu
$55,000
-
MMBtu
$14,440
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs