Assessment Year | 2016 |
---|---|
Principal Product | Metal Enclosure |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $100 M to 500M |
# of Employees | 174 |
Plant Area |
417,742
ft2
|
Annual Production | 16,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $500,266 | 6,614,263 |
kWh
|
$0.076 |
Electricity Demand | $85,080 | 16,530 |
kW-mo/yr
|
$5.15 |
Electricity Fees | $92,886 | - |
|
- |
Natural Gas | $153,642 | 23,656 |
MMBtu
|
$6.49 |
TOTAL YEARLY COSTS | $831,874 | |||
RECOMMENDED SAVINGS* | $157,057 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,917 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,840 | $1,000 |
$12,660
166,600
kWh
|
$1,180
-
kW-mo/yr
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $5,562 | $2,000 | - | - |
$5,562
-
MMBtu
|
- | |
03 | 2.7314: Reduce ventilation air | $102,120 | $52,500 |
$2,120
27,893
kWh
|
- | - | $100,000 | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,322 | $780 |
$1,167
15,362
kWh
|
$155
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $3,070 | $3,000 |
$3,070
40,395
kWh
|
- | - | - | |
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $16,120 | $35,000 |
$13,339
175,519
kWh
|
$2,781
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,376 | $16,500 |
$6,171
81,199
kWh
|
$1,205
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $454 | $1,300 |
$454
5,975
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,579 | $13,747 |
$3,745
49,271
kWh
|
$834
-
kW-mo/yr
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $179 | $780 |
$143
1,887
kWh
|
$36
-
kW-mo/yr
|
- | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,435 | $12,000 |
$2,229
29,327
kWh
|
$206
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $157,057 | $138,607 |
$45,098
593,428
kWh
|
$6,397
-
kW-mo/yr
|
$5,562
-
MMBtu
|
$100,000 | ||
TOTAL IMPLEMENTED | $27,917 | $30,307 |
$19,944
262,447
kWh
|
$2,411
-
kW-mo/yr
|
$5,562
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs