Assessment Year | 2015 |
---|---|
Principal Product | Scientific Glassware |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3221: Glass Containers |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
43,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,619 | 674,844 |
kWh
|
$0.12 |
Electricity Demand | $27,509 | 4,075 |
kW-mo/yr
|
$6.75 |
Electricity Fees | $7,289 | - |
|
- |
Natural Gas | $49,419 | 4,057 |
MMBtu
|
$12.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,936 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $702 | $35 |
$526
4,498
kWh
|
$176
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,655 | $4,000 |
$23,241
198,640
kWh
|
$7,736
-
kW-mo/yr
|
$(-10,322.0)
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,080 | $2,845 |
$7
59
kWh
|
$8,073
-
kW-mo/yr
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $214 | $105 |
$163
1,397
kWh
|
$51
-
kW-mo/yr
|
- | - | |
05 | 2.2136: Install / repair insulation on steam lines | $1,534 | $1,644 | - | - |
$1,534
-
MMBtu
|
- | |
06 | 2.2437: Recover waste heat from equipment | $1,473 | $1,950 | - | - |
$1,473
-
MMBtu
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $405 | $1,000 |
$304
2,600
kWh
|
$101
-
kW-mo/yr
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,304 | $9,400 |
$306
2,616
kWh
|
- |
$1,998
-
MMBtu
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,431 | $13,983 |
$2,693
23,019
kWh
|
$898
-
kW-mo/yr
|
- | $(-159.5) | |
10 | 2.1224: Replace boiler | $4,068 | $18,400 | - | - |
$4,068
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $42,866 | $53,362 |
$27,241
232,829
kWh
|
$17,034
-
kW-mo/yr
|
$(-1,249.8)
-
MMBtu
|
$(-159.5) | ||
TOTAL IMPLEMENTED | $10,936 | $5,629 |
$1,001
8,554
kWh
|
$8,401
-
kW-mo/yr
|
$1,534
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs