ITAC Assessment: LE0396
ITAC logo
ITAC Assessment: LE0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Scientific Glassware
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3221: Glass Containers
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 43,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,619 674,844
kWh
Electricity Demand $27,509 4,075
kW-mo/yr
Electricity Fees $7,289 -
Natural Gas $49,419 4,057
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,866 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,936

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $702 $35 $526
4,498
kWh
$176
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $20,655 $4,000 $23,241
198,640
kWh
$7,736
-
kW-mo/yr
$(-10,322.0)
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,080 $2,845 $7
59
kWh
$8,073
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $214 $105 $163
1,397
kWh
$51
-
kW-mo/yr
- -
05 2.2136: Install / repair insulation on steam lines $1,534 $1,644 - - $1,534
-
MMBtu
-
06 2.2437: Recover waste heat from equipment $1,473 $1,950 - - $1,473
-
MMBtu
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $405 $1,000 $304
2,600
kWh
$101
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $2,304 $9,400 $306
2,616
kWh
- $1,998
-
MMBtu
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $3,431 $13,983 $2,693
23,019
kWh
$898
-
kW-mo/yr
- $(-159.5)
10 2.1224: Replace boiler $4,068 $18,400 - - $4,068
-
MMBtu
-
TOTAL RECOMMENDED $42,866 $53,362 $27,241
232,829
kWh
$17,034
-
kW-mo/yr
$(-1,249.8)
-
MMBtu
$(-159.5)
TOTAL IMPLEMENTED $10,936 $5,629 $1,001
8,554
kWh
$8,401
-
kW-mo/yr
$1,534
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs