Assessment Year | 2015 |
---|---|
Principal Product | Breads and rolls |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 203 |
Plant Area |
182,000
ft2
|
Annual Production | 129,533,344
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $624,337 | 8,279,760 |
kWh
|
$0.075 |
Electricity Demand | $36,142 | 16,992 |
kW-mo/yr
|
$2.13 |
Electricity Fees | $24,574 | - |
|
- |
Natural Gas | $423,815 | 79,445 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $298,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,541 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $22,916 | $1,170 | - | - |
$22,916
-
MMBtu
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $703 | $70 |
$671
8,943
kWh
|
$32
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,552 | $656 |
$6,214
82,850
kWh
|
$339
-
kW-mo/yr
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $6,982 | $2,372 | - | - |
$6,982
-
MMBtu
|
|
05 | 2.7231: Use radiant heater for spot heating | $30,168 | $12,000 | - | - |
$30,168
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,773 | $1,000 |
$1,681
22,419
kWh
|
$92
-
kW-mo/yr
|
- | |
07 | 2.2511: Insulate bare equipment | $109 | $75 | - | - |
$109
-
MMBtu
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $41,985 | $49,800 |
$39,810
530,797
kWh
|
$2,175
-
kW-mo/yr
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,081 | $30,500 |
$21,495
286,604
kWh
|
$586
-
kW-mo/yr
|
- | |
10 | 2.2443: Re-use or recycle hot or cold process exhaust air | $119,994 | $200,000 | - | - |
$119,994
-
MMBtu
|
|
11 | 2.4321: Upgrade obsolete equipment | $17,674 | $30,425 |
$16,758
223,442
kWh
|
$916
-
kW-mo/yr
|
- | |
12 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,982 | $7,500 | - | - |
$3,982
-
MMBtu
|
|
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,886 | $29,120 |
$12,219
162,926
kWh
|
$667
-
kW-mo/yr
|
- | |
14 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,842 | $31,282 |
$10,793
143,906
kWh
|
$49
-
kW-mo/yr
|
- | |
15 | 2.3212: Optimize plant power factor | $28 | $145 | - |
$28
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $298,675 | $396,115 |
$109,642
1,461,887
kWh
|
$4,882
-
kW-mo/yr
|
$184,151
-
MMBtu
|
||
TOTAL IMPLEMENTED | $40,541 | $11,773 |
$6,214
82,850
kWh
|
$339
-
kW-mo/yr
|
$33,989
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs