ITAC Assessment: LE0362
ITAC logo
ITAC Assessment: LE0362
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Ductile Iron Pipe
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 217,800
ft2
Annual Production 70,000
ton
Production Hrs. Annual 1,920
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,350,626 18,252,804
kWh
Electricity Demand $278,239 59,580
kW-mo/yr
Electricity Fees $320,813 -
Natural Gas $1,392,055 224,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $464,597 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $287,194

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $162,427 $899,500 $96,768
1,307,674
kWh
$8,388
-
kW-mo/yr
- - $57,271
02 2.7135: Install occupancy sensors $764 $1,373 $764
10,322
kWh
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,545 $546 $1,152
15,566
kWh
$393
-
kW-mo/yr
- - -
04 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $41,942 $191,591 $29,165
394,131
kWh
$12,777
-
kW-mo/yr
- - -
05 2.3212: Optimize plant power factor $86,433 $302,515 - - - $86,433 -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $15,176 $3,043 - $15,176
-
kW-mo/yr
- - -
07 2.1121: Use insulation in furnaces to facilitate heating / cooling $114,240 $200,000 - - $114,240
-
MMBtu
- -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $33,088 $84,100 $23,730
320,681
kWh
$9,358
-
kW-mo/yr
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,982 $12,000 $8,011
108,270
kWh
$971
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $464,597 $1,694,668 $159,590
2,156,644
kWh
$47,063
-
kW-mo/yr
$114,240
-
MMBtu
$86,433 $57,271
TOTAL IMPLEMENTED $287,194 $1,112,046 $105,931
1,431,510
kWh
$9,752
-
kW-mo/yr
$114,240
-
MMBtu
- $57,271
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs