Assessment Year | 2013 |
---|---|
Principal Product | Wine and Grape Juice |
NAICS | 312130: Wineries |
SIC | 2084: Wines, Brandy, and Brandy Spirits |
Sales Range | $50 M to 100M |
# of Employees | 60 |
Plant Area |
184,000
ft2
|
Annual Production | 5,500
Tgal
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,823 | 1,979,309 |
kWh
|
$0.026 |
Electricity Demand | $59,762 | 9,694 |
kW-mo/yr
|
$6.16 |
Electricity Fees | $46,511 | - |
|
- |
Natural Gas | $141,707 | 21,541 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $156,728 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $97,831 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,256 | $3,010 | - |
$3,256
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40,049 | $56,100 |
$21,887
841,801
kWh
|
$17,094
-
kW-mo/yr
|
- | - | $1,068 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,699 | $7,698 |
$487
18,731
kWh
|
$62
-
kW-mo/yr
|
- | - | $1,150 | |
04 | 2.2442: Preheat combustion air with waste heat | $6,817 | $10,056 | - | - |
$6,817
-
MMBtu
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $911 | $1,000 |
$511
19,647
kWh
|
$400
-
kW-mo/yr
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,165 | $21,900 |
$3,461
133,110
kWh
|
$2,704
-
kW-mo/yr
|
- | - | - | |
07 | 2.3192: Use fossil fuel powered generator during peak demand periods | $71,337 | $190,000 | - | - | - | $71,337 | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,919 | $31,422 |
$13,991
538,138
kWh
|
$10,928
-
kW-mo/yr
|
- | - | - | |
09 | 2.7232: Replace existing hvac unit with high efficiency model | $1,575 | $16,800 |
$1,168
44,928
kWh
|
$407
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $156,728 | $337,986 |
$41,505
1,596,355
kWh
|
$34,851
-
kW-mo/yr
|
$6,817
-
MMBtu
|
$71,337 | $2,218 | ||
TOTAL IMPLEMENTED | $97,831 | $238,222 |
$15,159
583,066
kWh
|
$11,335
-
kW-mo/yr
|
- | $71,337 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs