| Assessment Year | 2012 |
|---|---|
| Principal Product | Custom Fabricated Products |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
82,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $157,264 | 1,175,020 |
kWh
|
$0.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $91,120 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $54,631 | $28,000 |
$54,631
407,697
kWh
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,684 | $1,000 |
$17,684
131,967
kWh
|
|
| 03 | 2.7135: Install occupancy sensors | $11,678 | $19,140 |
$11,678
86,700
kWh
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,020 | $1,562 |
$4,020
30,000
kWh
|
|
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $3,107 | $2,500 |
$3,107
23,190
kWh
|
|
| TOTAL RECOMMENDED | $91,120 | $52,202 |
$91,120
679,554
kWh
|
||
| TOTAL IMPLEMENTED | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs