Assessment Year | 2011 |
---|---|
Principal Product | Wood Furniture |
NAICS | 337122: Nonupholstered Wood Household Furniture Manufacturing |
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $50 M to 100M |
# of Employees | 20 |
Plant Area |
225,000
ft2
|
Annual Production | 150,000
pieces
|
Production Hrs. Annual | 2,066
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,974 | 1,363,740 |
kWh
|
$0.087 |
Electricity Demand | $37,809 | 7,170 |
kW-mo/yr
|
$5.27 |
Natural Gas | $44,132 | 4,040 |
MMBtu
|
$10.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,945 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $8,284 | $122,400 | - | - |
$8,284
-
MMBtu
|
- | |
02 | 2.4322: Use or replace with energy efficient substitutes | $8,133 | $5,085 |
$2,399
27,570
kWh
|
$5,734
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,830 | $28,998 |
$3,570
41,036
kWh
|
$2,740
-
kW-mo/yr
|
- | $520 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,665 | $400 |
$3,770
43,337
kWh
|
$895
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,126 | $26,983 |
$2,998
34,465
kWh
|
$1,054
-
kW-mo/yr
|
- | $74 | |
06 | 2.4112: Install soft-start to eliminate nuisance trips | $2,832 | $7,000 | - |
$2,832
-
kW-mo/yr
|
- | - | |
07 | 2.7135: Install occupancy sensors | $1,778 | $416 |
$1,778
20,431
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $297 | $530 |
$274
3,145
kWh
|
$23
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $36,945 | $191,812 |
$14,789
169,984
kWh
|
$13,278
-
kW-mo/yr
|
$8,284
-
MMBtu
|
$594 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs