ITAC Assessment: LE0323
ITAC logo
ITAC Assessment: LE0323
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Food Flavors
NAICS 311942: Spice and Extract Manufacturing
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 64
Plant Area 120,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,710 2,771,113
kWh
Electricity Demand $98,658 6,521
kW-mo/yr
Natural Gas $181,973 47,265
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,704 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,359

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $30,859 $30,000 $18,725
292,587
kWh
$12,134
-
kW-mo/yr
- -
02 2.9112: Use solar heat to heat water $11,446 $21,000 - - $11,446
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,384 $1,000 $5,343
83,478
kWh
$3,041
-
kW-mo/yr
- -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,933 $3,000 - $4,933
-
kW-mo/yr
- -
05 2.4322: Use or replace with energy efficient substitutes $2,867 $192 $189
2,955
kWh
$2,678
-
kW-mo/yr
- -
06 2.4112: Install soft-start to eliminate nuisance trips $2,360 $6,000 - $2,360
-
kW-mo/yr
- -
07 2.4322: Use or replace with energy efficient substitutes $1,240 $542 $1,013
15,825
kWh
$227
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $837 $2,921 $436
6,817
kWh
$393
-
kW-mo/yr
- $8
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $778 - $596
9,316
kWh
$182
-
kW-mo/yr
- -
TOTAL RECOMMENDED $63,704 $64,655 $26,302
410,978
kWh
$25,948
-
kW-mo/yr
$11,446
-
MMBtu
$8
TOTAL IMPLEMENTED $12,359 $9,921 $6,375
99,611
kWh
$5,976
-
kW-mo/yr
- $8
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs