ITAC Assessment: LE0267
ITAC logo
ITAC Assessment: LE0267
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product bottled water
NAICS 312112: Bottled Water Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 322
Plant Area 385,000
ft2
Annual Production 454,272,000
units
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,613,312 70,230,247
kWh
Electricity Demand $823,235 117,030
kW-mo/yr
Natural Gas $816,078 98,061
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $390,992 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $136,305

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 4.652: Replace existing equipment with more suitable substitutes $198,263 $200,000 $142,338
2,790,945
kWh
$25,266
-
kW-mo/yr
- $30,659
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $41,140 $6,000 - $41,140
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $36,169 $30,000 $30,411
596,286
kWh
$5,758
-
kW-mo/yr
- -
04 2.2113: Repair or replace steam traps $31,944 $2,000 - - $31,944
-
MMBtu
-
05 2.2442: Preheat combustion air with waste heat $21,795 $30,000 - - $21,795
-
MMBtu
-
06 2.5195: Change product design to reduce energy requirements $26,495 $31,435 $22,277
436,800
kWh
$4,218
-
kW-mo/yr
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $9,200 $3,000 - - $9,200
-
MMBtu
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,134 $1,500 $6,720
131,763
kWh
$1,414
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,723 $1,000 $3,971
77,870
kWh
$752
-
kW-mo/yr
- -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $13,129 $300,000 $11,090
211,411
kWh
$2,039
-
kW-mo/yr
- -
TOTAL RECOMMENDED $390,992 $604,935 $216,807
4,245,075
kWh
$80,587
-
kW-mo/yr
$62,939
-
MMBtu
$30,659
TOTAL IMPLEMENTED $136,305 $342,000 $45,472
885,567
kWh
$49,689
-
kW-mo/yr
$41,144
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs