ITAC Assessment: LE0204
ITAC logo
ITAC Assessment: LE0204
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Asphalt Products
NAICS 324122: Asphalt Shingle and Coating Materials Manufacturing
SIC 2952: Asphalt Felts and Coatings
Sales Range $10
M
to 50
M
# of Employees 15
Plant Area 70,000
ft2
Annual Production 30,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,350 928,200
kWh
Electricity Demand $34,987 7,762
kW-mo/yr
Natural Gas $277,333 36,898
MMBtu
Fuel Oil #2 $75,757 11,327
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,500 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,631

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings
01 3.6124: Burn waste oil for heat $18,746 $3,000 - - - $18,746
-
MMBtu
02 2.2123: Insulate feedwater tank $18,286 $8,304 - - $18,286
-
MMBtu
-
03 2.6124: Establish equipment maintenance schedule $4,345 $2,750 $4,345
77,584
kWh
- - -
04 2.2414: Use waste heat from hot flue gases to preheat $3,339 $6,000 - - $3,339
-
MMBtu
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,784 $600 $1,418
25,322
kWh
$366
-
kW-mo/yr
- -
TOTAL RECOMMENDED $46,500 $20,654 $5,763
102,906
kWh
$366
-
kW-mo/yr
$21,625
-
MMBtu
$18,746
-
MMBtu
TOTAL IMPLEMENTED $22,631 $11,054 $4,345
77,584
kWh
- $18,286
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs