ITAC Assessment: LE0188
ITAC logo
ITAC Assessment: LE0188
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Windshield Water Nozzles
NAICS 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 89,000
ft2
Annual Production 48,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $177,771 3,906,890
kWh
Electricity Demand $93,679 8,926
kW-mo/yr
Natural Gas $10,648 1,242
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,589 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,266

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,732 $1,000 $2,429
52,793
kWh
$13,303
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $9,843 $17,200 - - $9,843
03 2.4226: Use / purchase optimum sized compressor $6,132 $8,028 $4,662
101,348
kWh
$1,470
-
kW-mo/yr
-
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,694 $2,500 - $4,694
-
kW-mo/yr
-
05 2.4238: Do not use compressed air for personal cooling $3,459 $1,200 $2,378
51,692
kWh
$1,081
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,947 $11,665 $1,543
33,543
kWh
$1,404
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $1,782 $3,900 $1,782
38,743
kWh
- -
TOTAL RECOMMENDED $44,589 $45,493 $12,794
278,119
kWh
$21,952
-
kW-mo/yr
$9,843
TOTAL IMPLEMENTED $19,266 $35,265 $3,325
72,286
kWh
$6,098
-
kW-mo/yr
$9,843
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs