ITAC Assessment: LE0181
ITAC logo
ITAC Assessment: LE0181
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Laminated Hardwood
NAICS 321999: All Other Miscellaneous Wood Product Manufacturing
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 120,000
ft2
Annual Production 4,500,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,794 2,042,641
kWh
Electricity Demand $81,816 8,694
kW-mo/yr
Natural Gas $5,982 515
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $185,568 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,765

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Wood Savings Solid Waste (non-haz) Savings
01 3.5311: Recover and reuse waste material $132,275 $20,000 - - - - - $132,275
-
lb
02 2.1233: Analyze flue gas for proper air/fuel ratio $37,431 $2,000 - - - - $37,431
-
MMBtu
-
03 2.1393: Use steam sparging or injections in place of indirect heating $5,226 $10,000 - - - $5,226
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,768 $200 $1,685
37,418
kWh
$2,083
-
kW-mo/yr
- - - -
05 2.6218: Turn off equipment when not in use $3,160 - $3,160
70,225
kWh
- - - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,566 - $1,366
30,355
kWh
$1,200
-
kW-mo/yr
- - - -
07 2.3212: Optimize plant power factor $860 $4,250 - - $860 - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $282 - $282
6,263
kWh
- - - - -
TOTAL RECOMMENDED $185,568 $36,450 $6,493
144,261
kWh
$3,283
-
kW-mo/yr
$860 $5,226
-
MMBtu
$37,431
-
MMBtu
$132,275
-
lb
TOTAL IMPLEMENTED $43,765 $2,200 $3,051
67,773
kWh
$3,283
-
kW-mo/yr
- - $37,431
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Wood Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs