ITAC Assessment: LE0173
ITAC logo
ITAC Assessment: LE0173
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Steel Wire Rope and Strand
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 479
Plant Area 600,000
ft2
Annual Production 24,000
ton
Production Hrs. Annual 8,568
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $980,742 20,517,700
kWh
Electricity Demand $273,211 48,034
kW-mo/yr
Natural Gas $900,672 154,953
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,716 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $37,011 - - $37,011
-
kW-mo/yr
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $32,033 - $27,461
574,508
kWh
$4,572
-
kW-mo/yr
- -
03 2.8123: Pay utility bills on time $14,409 - - - - $14,409
04 2.8123: Pay utility bills on time $10,900 - - - - $10,900
05 2.2426: Use waste heat from flue gases to heat space conditioning air $6,047 $10,000 - - $6,047
-
MMBtu
-
06 2.1233: Analyze flue gas for proper air/fuel ratio $2,247 $750 - - $2,247
-
MMBtu
-
07 2.6218: Turn off equipment when not in use $1,069 - $1,069
22,362
kWh
- - -
TOTAL RECOMMENDED $103,716 $10,750 $28,530
596,870
kWh
$41,583
-
kW-mo/yr
$8,294
-
MMBtu
$25,309
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs