Assessment Year | 2003 |
---|---|
Principal Product | Metal Stamping |
NAICS | 333514: Special Die and Tool, Die Set, Jig, and Fixture Manufacturing |
SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
77,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $163,817 | 2,391,400 |
kWh
|
$0.069 |
Electricity Demand | $72,926 | 6,062 |
kW-mo/yr
|
$12.03 |
Natural Gas | $49,581 | 6,669 |
MMBtu
|
$7.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,242 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,810 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $12,638 | - |
$8,409
121,875
kWh
|
$4,229
-
kW-mo/yr
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,790 | - |
$4,336
62,843
kWh
|
$1,454
-
kW-mo/yr
|
- | |
03 | 2.3191: Use demand controller or load shedder | $3,645 | $6,000 | - |
$3,645
-
kW-mo/yr
|
- | |
04 | 2.3212: Optimize plant power factor | $2,512 | - | - | - | $2,512 | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $1,863 | $608 |
$1,395
20,217
kWh
|
$468
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,050 | $10,345 |
$1,532
22,370
kWh
|
$518
-
kW-mo/yr
|
- | |
07 | 2.7135: Install occupancy sensors | $1,080 | $375 |
$1,080
15,655
kWh
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $664 | $100 |
$496
7,251
kWh
|
$168
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $30,242 | $17,428 |
$17,248
250,211
kWh
|
$10,482
-
kW-mo/yr
|
$2,512 | ||
TOTAL IMPLEMENTED | $18,810 | $6,708 |
$10,300
149,343
kWh
|
$8,510
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs