ITAC Assessment: LE0170
ITAC logo
ITAC Assessment: LE0170
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Insulation Facings (Paper Laminate)
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range n/a
# of Employees 103
Plant Area 155,000
ft2
Annual Production 1,000,000
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $376,987 5,130,800
kWh
Electricity Demand $146,189 15,496
kW-mo/yr
Natural Gas $126,243 14,518
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $215,254 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,966

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $210,423 $300,000 $168,780
2,296,320
kWh
$41,643
-
kW-mo/yr
-
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $2,647 $7,000 $2,647
36,016
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $952 - $952
12,948
kWh
- -
04 2.2625: Chill water to the highest temperature possible $367 - $367
4,992
kWh
- -
05 2.2511: Insulate bare equipment $440 $560 - - $440
-
MMBtu
06 2.7135: Install occupancy sensors $425 $825 $425
5,781
kWh
- -
TOTAL RECOMMENDED $215,254 $308,385 $173,171
2,356,057
kWh
$41,643
-
kW-mo/yr
$440
-
MMBtu
TOTAL IMPLEMENTED $3,966 $7,000 $3,966
53,956
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs