ITAC Assessment: IC0060
ITAC logo
ITAC Assessment: IC0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Surfactants for Detergents, etc
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 115
Plant Area 1,132,560
ft2
Annual Production 119,000,000
lb
Production Hrs. Annual 7,344
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $485,432 9,577,325
kWh
Electricity Demand $55,676 15,509
kW-mo/yr
Electricity Fees $41,695 -
Natural Gas $1,080,576 297,767
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $470,450 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $361,521

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.2135: Repair and eliminate steam leaks $148,006 $13,000 - - $137,447
-
MMBtu
- - - $10,559
-
Tgal
02 2.2136: Install / repair insulation on steam lines $8,832 $13,240 - - $8,832
-
MMBtu
- - - -
03 2.4133: Use most efficient type of electric motors $8,390 $20,640 $7,678
139,605
kWh
$712
-
kW-mo/yr
- - - - -
04 2.2128: Use steam condensate for hot water supply (non-potable) $163,590 $170,491 - - $97,629
-
MMBtu
- - - $65,961
-
Tgal
05 2.3321: Use steam pressure reduction to generate power $92,294 $190,000 $90,732
1,649,664
kWh
$8,271
-
kW-mo/yr
$(-4,709.0)
-
MMBtu
- $(-2,000.0) - -
06 2.4131: Size electric motors for peak operating efficiency $9,196 $22,867 $8,634
156,976
kWh
$562
-
kW-mo/yr
- - - - -
07 2.2135: Repair and eliminate steam leaks $11,372 $5,850 - - $11,372
-
MMBtu
- - - -
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $7,439 $6,850 - - $7,439
-
MMBtu
- - - -
09 2.2437: Recover waste heat from equipment $17,626 $13,998 - - $17,626
-
MMBtu
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $3,705 $11,354 $2,808
51,026
kWh
$298
-
kW-mo/yr
- $96 - $503 -
TOTAL RECOMMENDED $470,450 $468,290 $109,852
1,997,271
kWh
$9,843
-
kW-mo/yr
$275,636
-
MMBtu
$96 $(-2,000.0) $503 $76,520
-
Tgal
TOTAL IMPLEMENTED $361,521 $248,573 $10,486
190,631
kWh
$1,010
-
kW-mo/yr
$272,906
-
MMBtu
$96 - $503 $76,520
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs