Assessment Year | 2003 |
---|---|
Principal Product | Pre-Painted Sheet Steel |
NAICS | 331221: Rolled Steel Shape Manufacturing |
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $10 M to 50M |
# of Employees | 48 |
Plant Area |
50,000
ft2
|
Annual Production | 7,800
ton
|
Production Hrs. Annual | 2,288
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $179,724 | 1,079,867 |
kWh
|
$0.17 |
Electricity Demand | $97,665 | 8,168 |
kW-mo/yr
|
$11.96 |
Natural Gas | $65,300 | 6,799 |
MMBtu
|
$9.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,662 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $658 | - |
$658
8,656
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,185 | $300 |
$3,936
51,796
kWh
|
$3,249
-
kW-mo/yr
|
- | |
03 | 2.2113: Repair or replace steam traps | $3,519 | $3,000 | - | - |
$3,519
-
MMBtu
|
|
04 | 2.2123: Insulate feedwater tank | $363 | $183 | - | - |
$363
-
MMBtu
|
|
05 | 2.2136: Install / repair insulation on steam lines | $5,016 | $2,582 | - | - |
$5,016
-
MMBtu
|
|
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,485 | $750 | - | - |
$5,485
-
MMBtu
|
|
07 | 2.7135: Install occupancy sensors | $83 | $150 |
$83
1,087
kWh
|
- | - | |
TOTAL RECOMMENDED | $22,309 | $6,965 |
$4,677
61,539
kWh
|
$3,249
-
kW-mo/yr
|
$14,383
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,662 | $3,750 |
$658
8,656
kWh
|
- |
$9,004
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs