| Assessment Year | 2002 |
|---|---|
| Principal Product | Speacialty Chemicals |
| NAICS |
n/a
|
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 108 |
| Plant Area |
49,706
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $144,938 | 1,382,500 |
kWh
|
$0.10 |
| Electricity Demand | $27,764 | 4,059 |
kW-mo/yr
|
$6.84 |
| Natural Gas | $47,265 | 4,602 |
MMBtu
|
$10.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,176 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $567 | $1,000 |
$403
4,752
kWh
|
$164
-
kW-mo/yr
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $993 | - |
$993
10,998
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,031 | $300 |
$1,333
15,719
kWh
|
$1,698
-
kW-mo/yr
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $692 | - |
$497
5,865
kWh
|
$195
-
kW-mo/yr
|
- | - | |
| 05 | 2.2123: Insulate feedwater tank | $121 | $260 | - | - |
$121
-
MMBtu
|
- | |
| 06 | 2.2136: Install / repair insulation on steam lines | $1,804 | $535 | - | - |
$1,804
-
MMBtu
|
- | |
| 07 | 3.6192: Use a less expensive method of waste removal | $1,390 | - | - | - | - |
$1,390
-
lb
|
|
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,496 | - | - | - | - |
$3,496
-
lb
|
|
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,033 | $750 | - | - |
$1,033
-
MMBtu
|
- | |
| 10 | 2.7111: Reduce illumination to minimum necessary levels | $1,308 | $990 |
$1,001
11,806
kWh
|
$307
-
kW-mo/yr
|
- | - | |
| 11 | 2.7135: Install occupancy sensors | $210 | $150 |
$210
2,480
kWh
|
- | - | - | |
| 12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $690 | $4,095 |
$503
5,928
kWh
|
$187
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $15,335 | $8,080 |
$4,940
57,548
kWh
|
$2,551
-
kW-mo/yr
|
$2,958
-
MMBtu
|
$4,886
-
lb
|
||
| TOTAL IMPLEMENTED | $7,176 | $6,395 |
$3,830
44,451
kWh
|
$2,192
-
kW-mo/yr
|
$1,154
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs