ITAC Assessment: LE0120
ITAC logo
ITAC Assessment: LE0120
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Woven mesh and drawn wire
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $50
M
to 100
M
# of Employees 480
Plant Area 350,000
ft2
Annual Production 5,500,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,002,944 17,693,700
kWh
Electricity Demand $300,277 33,169
kW-mo/yr
Natural Gas $687,369 138,985
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $97,740 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,228

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $43,479 $7,500 - $43,479
-
kW-mo/yr
-
02 2.1113: Reduce combustion air flow to optimum $3,995 $1,000 - - $3,995
-
MMBtu
03 2.4312: Improve lubrication practices $13,290 $800 $13,290
332,244
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $22,381 - $16,051
583,916
kWh
$6,330
-
kW-mo/yr
-
05 2.2511: Insulate bare equipment $2,562 $200 $2,562
64,044
kWh
- -
06 2.2437: Recover waste heat from equipment $12,033 $18,460 - - $12,033
-
MMBtu
TOTAL RECOMMENDED $97,740 $27,960 $31,903
980,204
kWh
$49,809
-
kW-mo/yr
$16,028
-
MMBtu
TOTAL IMPLEMENTED $42,228 $2,000 $31,903
980,204
kWh
$6,330
-
kW-mo/yr
$3,995
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs